CCS world projects: Niederaussem
Project Overview
RWE, BASF and Linde have built a pilot plant is capable of capturing roughly 300 kilograms of CO2 per hour from a partial flow of power station flue gases at the Niederaussem lignite power plant. Capture efficiency is 90 percent.
Project Type
Capture & Storage
Location
Niederaussem, Bergheim, Germany
Type of CO2 Storage Operation
Onshore saline aquifer ![]()
Major Stakeholders
Project Scale
Commercial
Project Start Year: 2006
| 2015 | |||
![]() |
![]() |
| Unknown | |
| 2.3 Mt | |
| Unknown |
| Additional Data | ||
| Depth of Injection Interval (average) | Unknown | |
| Type of Reservoir | Unknown | |
| Type of Seal | Unknown | |
| Distance Source to Sink | Unknown |
Method of CO2 Delivery
Pipeline
Injected Gas Composition
Unknown
Project Cost
€200 million for the pipeline and CO2 storage operations