The existing capture and use of CO2 in greenhouses will be expanded to 1.5 Mt per year. Also, about 1Mt CO2 will be stored in depleted gas fields (one onshore, and one onshore) beginning in 2010. Following these pilot, large scale pilots will aim for CCS at a rate of 3.5Mt per year. By 2025 the CO2 capture from the Rotterdam harbour will amount to some 20 Mt per year.
Project Type
Capture & Storage
Location
Barendrecht & Offshore from Haarlem
Type of CO2 Storage Operation
Depleted gas field![]()
Major Stakeholders
The Dutch government
The Clinton Climate Intitiative
Project Scale
Pilot project
Project Start Year: 2010
| 2010 | |||
![]() |
![]() |
| Unknown | |
| Unknown | |
| Unknown |
| Additional Data | ||
| Depth of Injection Interval | Unknown | |
| Type of Reservoir | Unknown | |
| Type of Seal | Unknown | |
| Distance Source to Sink | Unknown |
Method of CO2 Delivery
Pipeline
Injected Gas Composition
Unknown
Project Cost
Unknown